Site icon eeediary.com

Power Transformer Testing and commissioning

Power transformer testing and commissioning are critical stages in ensuring the reliability, safety, and optimal performance of power transformers in electrical networks. The process involves a series of tests and procedures conducted at different stages, from manufacturing to installation.

Here are the key stages of power transformer testing and commissioning:

1. Factory Acceptance Testing (FAT):

1.1. Purpose: To ensure that the transformer meets specified design and performance criteria before it is shipped to the installation site.

1.2. Tests Conducted:- Measurement of winding resistance. – Turns ratio test. – Insulation resistance test. – Excitation current test. – Polarity and phase-relation test. – Impedance voltage and load loss test.

2. Transportation and Handling:

2.1. Purpose: To verify that the transformer has not been damaged during transportation and handling.

2.2. Activities:- Visual inspection for external damage. – Checking oil levels and integrity of bushings.

3. Site Acceptance Testing (SAT):

3.1. Purpose: To confirm that the transformer was not damaged during transportation and to ensure it is ready for installation.

3.2. Tests Conducted:- Insulation resistance test. – Transformer turns ratio test. – Winding resistance measurement. – Polarity and phase-relation test.

Dielectric tests, including power frequency withstand voltage test.

4. Installation and Pre-commissioning:

4.1. Purpose: To ensure that the transformer is properly installed and connected to the electrical system.

4.2. Activities:- Checking oil levels and filling if necessary. – Checking and tightening electrical connections. – Verifying correct tap changer operation.

5. Energization and Functional Tests:

5.1. Purpose: To verify the transformer’s performance under load conditions and ensure proper functioning.

5..2. Tests Conducted:- Load loss and impedance tests. – Measurement of no-load loss and current. – Short circuit withstand test. – Temperature rise test.

6. Oil Filtration and Treatment:

6.1. Purpose: To ensure the transformer’s insulating oil meets specified cleanliness and dielectric strength requirements.

6.2. Activities:- Filtration of the transformer oil. – Testing for dielectric strength and moisture content.

7. Commissioning Tests:

7.1. Purpose: To validate the transformer’s performance and integration into the overall electrical system

7.2. Tests Conducted:- Voltage ratio test.Vector group verification. – Parallel operation test (if applicable). – Verification of protective relay settings.

8. Site Documentation and Handover:

8.1. Purpose: To provide comprehensive documentation of the testing and commissioning process for future reference and to facilitate the handover to the end-user.

8.2. Activities:- Compilation of test reports and documentation. – Training for operating and maintenance personnel. – Handover of all relevant documentation.

The testing and commissioning of power transformers are integral to ensuring the reliability, safety, and efficiency of electrical power systems. These stages involve a combination of factory and site-based tests, inspections, and procedures to confirm that the transformer meets specified standards and performs as intended within the operational environment

Exit mobile version